The Issue / Problem

Woolmer Hill Secondary School required the replacement of ageing windows and failed glazing systems across multiple buildings. The existing frames and glazing had deteriorated over time, leading to heat loss, reduced internal comfort, and a façade that no longer met modern performance or aesthetic standards.

Instruction to proceed was received less than three weeks prior to mobilisation, with all works programmed for completion during the school holidays. During removal of the existing façade systems, hidden defects and unforeseen constraints were identified, requiring responsive management and programme control.

Acting as Principal Contractor, we ensured full compliance with CDM Regulations while coordinating multiple trades within a live educational setting in preparation for the new academic term.

Woolmer Hill, Surrey

The Outcome

The project delivered a complete transformation to a modern aluminium glazing system across multiple school buildings.

The new façade significantly improved visual consistency and appearance, while enhanced thermal efficiency increased comfort within teaching spaces. The durable, low-maintenance system provides long-term value and performance for the school.

All works were completed smoothly and safely during the school holidays, ensuring the buildings were fully prepared for staff and students to return, with zero disruption to term-time operations.

Our Solution

We delivered a comprehensive façade upgrade designed to improve performance, safety and long-term durability, including:

  • Full replacement of existing glazing units with a modern aluminium system incorporating Kestrel frames

  • Removal of failed seals, defective glazing, and deteriorated components

  • Integration of enhanced safety features, improved ventilation, and upgraded thermal performance

  • Careful phasing and programming to ensure all buildings were ready for occupation at the end of the holiday period

  • Full Principal Contractor duties under CDM Regulations, coordinating multiple trades safely and efficiently

At a Glance

Overcoming Challenges

  • Mobilised to site within a three-week instruction-to-commencement timeframe

  • Proactively identified and resolved concealed façade defects during strip-out

  • Undertook pre-construction surveys and coordination meetings outside school hours to minimise disruption

  • Implemented safe access solutions using MEWPs and mobile scaffold towers across multiple elevations

  • Maintained clearly segregated work zones to safeguard pupils, staff, and visitors

  • Delivered installation works in strict accordance with manufacturer specifications to ensure long-term performance

For more information, expert advice, or a no-obligation quote, contact us or chat with us online

More Case Studies

  • Care Home, Stanmore

    Find out how Evander supported a client with repairs at a 72-bed care home in Stanmore, London.

  • High Street Bank in Streatham, London

    Find out about how Evander responded to urgent glazing damage at a high street bank in London.

  • Pulse Testing, Windows and PIV Installation in Dunston, Gateshead

    Evander reduced internal noise for a customer near the A1 using acoustic glazing and PIV.

  • Care Home, Stanmore

    Find out how Evander supported a client with repairs at a 72-bed care home in Stanmore, London.

  • High Street Bank in Streatham, London

    Find out about how Evander responded to urgent glazing damage at a high street bank in London.